Implementation Schedule.

Table 2-2-1: Comparison of Original and Actual Schedule

Items

Original

Actual

Selection of Consultant

Establishment of PMU

Forest and Biodiversity Conservation

Eco-tourism

Joint Forest Management

Supporting Activities

Consulting Services

Project Completion Date*

April 2010- December 2010

April 2010

June 2010- March 2020


September 2010- March 2020

June 2010- March 2020

April 2010- March 2020

January 2011- March 2020

March 2020

As of (Date of Revision)

Please state not only the

most updated schedule

but also other past 

revisions chronologically.

*Project Completion was defined as completion of Forest and Biodiversity Conservation.